be_ixf;ym_202412 d_21; ct_50

Creative chockfast orange solution avoids costly machining work

13,000mm x 400mm skid foundation onboard Norwegian jack up oil rig

Goltens was contacted by a shipyard to evaluate a challenge onboard a Jack Up Drilling Rig undergoing a refit on the West Coast of Norway.

The customer required a foundation for a skid foundation for a crane that could withstand a total load of more than 100 tons. Upon evaluation, Goltens determined that the foundation could be machined but that there was a much more efficient solution to the problem that would take significantly less time to complete.

As the long time distributor for ITW Polymer Technologies’ Chockfast product , Goltens saw an opportunity to avoid a costly in-situ machining project. After performing the calculations and engineering the alternative solution, Goltens determined that the Chockfast foundation could more than support the tonnage requirements of the skid.

Goltens presented the alternative solution to the customer and Goltens was given the order to proceed.

  • Goltens technicians preparing the skid for Chockfasting

    Goltens technicians preparing the skid for Chockfasting

  • Plastazote molds for the chocking compound installed below the raised skid

    Plastazote molds for the chocking compound installed below the raised skid

  • Goltens technician pouring Chockfast Orange compound into foundation mold

    Goltens technician pouring Chockfast Orange compound into foundation mold

  • Chockfast foundation after pouring

    Chockfast foundation after pouring

PROJECT FACTS

OIL RIG SKID CHOCKFASTING
Length of Foundation: 13,000mm
Width of Foundation: 400mm
Thickness of Foundation: 20-25mm
Liters of Chockfast Orange used: 350 Liters

SKID FOUNDATION WORK SCOPE

  • Engineering/Design of Chockfast Orange foundation
  • Fabrication of Plastazote molds for the Chocking material
  • Pouring of 350 liters of Chockfast Orange compound to support the 13,000mm x 400mm H Beam foundation of skid.

RESULTS

The total job was completed by Goltens in only 3 days. Inspection of the foundation by the customer was satisfactory and Goltens expects follow on orders for the execution of similar work for additional skid foundations.

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/creative-chockfast-orange-solution-avoids-costly-machining-work
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=creative-chockfast-orange-solution-avoids-costly-machining-work&page=
Loaded Template: single-resources.php
Search Goltens ×