be_ixf;ym_202412 d_21; ct_50

TriYard shipyard - Cable Layer Vessel “Lewek Constellation”

2 x 6 MW Stern Thruster Inverted Flange Machining

Goltens has a long history of taking on the most challenging in-situ machining work and providing our customers a full package solution. So when Goltens was contacted by TriYard Shipyard Co Ltd in Vietnam, part of the Ezra Group, to undertake large-scale flange facing of 2 – 6 Megawatt Stern Thruster flanges on a Cable Laying Vessel, Goltens jumped at the opportunity.

While the flange size itself, with an outside diameter of 4,700mm and an inside diameter of 2,850mm, presented no challenge to the equipment, the logistics and positioning were a different story.

The flange position required Goltens to mount the flange facing equipment inverted at the top of 12 meter staging. This required Goltens to fabricate a special lifting bracket to hoist the 6000i Facing Machine into the Thruster Tunnel once it was atop the staging. DTI equipment was then used to ensure that the machine was in the correct position to enable machining to commence.

  • Lewek Constellation

    Lewek Constellation

  • Goltens in-place machinists conducting large diameter inverted flange facing

    Inverted flange facing in progress

  • Goltens in-place machinists conducting large diameter inverted flange facing

    4.7 meter diamater flange machining

PROJECT FACTS

PH1002/LEWEK CONSTELLATION 6MW Stern Thruster Flange – Inverted On-Site Machining
Customer: TRIYARD Shipyard Co Ltd. Vung Tau- Vietnam
Flange size: OD 4700mm x ID 2850mm x 40 mm thick
Tolerance of flange flatness max: 0.15 mm
Quantity: 2 flanges
Class surveyor: DNV

ON-SITE FLANGE MACHINING CONSISTED OF

  • Dial gauge flatness checking & inverted milling of thruster OD 4,700mm x ID 2,850mm x 40 mm thick by large flange facing machine 6000i.
  • Carried out roughness checking on flange surface to confirm final tolerances were in accordance with specifications.

FLANGE FACING RESULTS

The job was completed ahead of time with a job process approved by class. The end result was within the tolerances set by the yard and the Thruster Supplier.

CUSTOMER TESTIMONIAL:

“Thank you very much for your great support. Your team did very good job from progress and technical point of view” – David Zhang, General Manager, TriYard – Vung Tau

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/in-situ-flange-facing-case-study
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=in-situ-flange-facing-case-study&page=
Loaded Template: single-resources.php
Search Goltens ×