be_ixf;ym_202412 d_21; ct_100

3 Marine Diesel Engines Overhauled For Cutter Suction Dredger in less than 3 weeks

24,000 hour pms of 3 DEUTZ SBV8M540

One of the world’s most powerful self propelled cutter dredger Leonardo Da Vinci, with over 20,000 KW installed diesel power, required a full overhaul and reconditioning of vessels 3 main engines after more than 24,000 running hours. Timelines were extremely tight and logistics for the project extremely challenging. This project proved the value of the service agreement between Denis Diesel and Goltens Dubai to fulfill the task within a very demanding schedule of 3 weeks.

The day after the vessel berthed in DUQM yard in Oman, a team of 1 Senior Supervisor, 1 Foreman and 6 technicians boarded the vessel and worked around the clock together with 4 service engineers from Denis to perform the engine dismantling works.

The engine components were transported from DUQM OMAN to Goltens Dubai (a total distance of 1500 KM with 2 custom process stoppages between borders). Working 24/7 in Goltens’ workshop, all diesel engine components were completely reconditioned and dispatched in less than 1 week in accordance with the project plan.

  • Cylinder Installation

    Cylinder Installation

  • Diesel engine overhaul

    Piston Work

  • Diesel engine overhaul

    Cylinder Installation

  • Diesel engine overhaul

    End Cover work

MARINE DIESEL ENGINE OVERHAUL PROJECT FACTS

LEONARDO DA VINCI
Ship Type: Cutter Suction Dredger
Gross Tonnage: 5,760
Dead Weight: 1,490
Year Built: 1985
Engine: DEUTZ SBV 8M540
Engine Output: 3,295 kW
RPM: 600 RPM

MARINE DIESEL ENGINE REPAIRS

  • Supplied a team of 1 Senior Supervisor, 1 Foreman & 6 technicians for onboard repairs
  • Full reconditioning of 24 cylinder heads and all attachments
  • Full inspection/calibration of Pistons
  • Honing & skimming of liner landing surfaces
  • Inspection of 2 main lube oil pumps
  • Ultrasonic Cleaning of Air Coolers
  • Reassembly and operational testing of engines

MARINE DIESEL ENGINE OVERHAUL RESULTS

Only 18 days after project start, Goltens and Denis handed 3 fully operational engines back to the ship’s crew and the vessel returned to operation with full efficiency.

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/marine-diesel-engine-overhaul-case-study
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=marine-diesel-engine-overhaul-case-study&page=
Loaded Template: single-resources.php
Search Goltens ×