be_ixf;ym_202412 d_26; ct_50

TechCross BWTS Retrofit for LNG Carrier

ANOTHER SUCCESSFUL TECHCROSS BWTS INSTALLATION BY GOLTENS GREEN TECHNOLOGIES IN ASIA AT SEMBAWANG SHIPYARD IN SINGAPORE

Goltens Singapore was contracted by a well known LNG Ship Owner to execute 3D scanning, design engineering, material supply & installation supervision on one of their vessels. The BWTS installation comprises of one of the world’s largest Ballast Water Treatment System to be installed onboard vessel to comply with IMO regulations.

  • TechCross Ballast Water treatment system retrofit design overview

    TechCross BWTS Design Overview

  • Installation overview of TechCross BWTS installation port side

    Installation overview of Port Side Flow Meter & ECU 5 & 6

  • Installation overview of TechCross BWTS installation starboard side

    Installation overview of Starboard Side (ECU 2 & 3)

  • Prefabricated pipe spools for TechCross BWTS retrofit intallation

    Prefabricated Big Bore Pipes supplied by Goltens

  • Cable drums supplied by Goltens for TechCross BWTS retrofit

    Goltens supplied Cable Drums

  • Valves supplied by Goltens for TechCross BWTS retrofit

    Goltens supplied valves of various sizes

  • Removal of pipes and demolition for TechCross BWTS retrofit

    Removal of Existing Pipes and Demolition process

  • Installation of tie in points for TechCross BWTS retrofit

    Installation of tie in points

  • Installation of Big Bore spools for TechCross BWTS retrofit

    Installation of Big Bore Spools with ECUs

DETAILED SCOPE OF WORK:

  • 3D scanning & vessel survey
  • Basic and Detail engineering
  • Class approvals
  • Procurement & Prefabrication
  • Supply of Material to Shipyard (Big Bore piping, Small Bore piping, Site run Piping & fittings, Valves & Cable Drums)
  • Installation supervision

TECHNICAL DESCRIPTION:

Vessel Length (LOA) 288.2m × 43.4m
Vessel DWT 83,068 T
Built Year & Yard 2004 – DSME, Korea
Gross Tonnage 97,561 T
BWTS ECS-3,200 B x 2 Sets
Ballast Pump 3,100 m3/h x 3 sets

DESIGN & ENGINEERING PLANNING:

Upon contract agreement, Goltens Singapore performed 3D laser scanning with a team of proficient engineers onboard the vessel. Upon completion, the 3D scans were registered and Goltens Singapore embarked on the design engineering works with 3D modeling software. Goltens Singapore worked rigorously to develop the Engineering Design and upon approval from vessel Representatives & Class the prefabrication & procurement of materials & equipment respectively was begun.

From the outset, the primary constraint of the project was the limited size of area surrounding the ballast pumps as the Maker’s (TechCross) equipment were both large in size and quantity. Despite these constraints, the engineering team scrutinized the designs repeatedly to ensure that the design was able to optimize the space management.

During the prefabrication phase, Goltens Singapore Team conducted numerous inspections to ensure that the quality & integrity of prefabricated pipes were up to satisfactory standards. Upon completion of pre-fabrication, Non- Destructive Testing was carried out by qualified Goltens personnel and witnessed by Vessel representatives.

INSTALLATION PHASE:

The installation was carried out by Sembawang Shipyard Contractors for a duration of 20 days & was completed successfully.

The installation phase was carried out in 5 different stages simultaneously.

  • Stage 1: Remove the existing pipes to install the tie in spools, lift out the existing pipes (demolition) and install the newly fabricated big bore (600A) pipes.
  • Stage 2: Fabricate & install the foundation supports for the equipment (Electro Chamber Unit, Power Distribution Equipment, Auto Neutralization Unit & TRO Sensor Unit)
  • Stage 3: Lifting the equipment safely into the lowest deck of the Engine Room and securing the equipment.
  • Stage 4: Completion of electrical works including: cable pulling, cable termination at main switchboards, power distribution equipment and equipment onsite.
  • Stage 5: Installation of the small-bore piping between the equipment and big bore spools.Over the entire installation phase, Goltens Singapore guided the shipyard contractors meticulously to ensure there were no delays to the project schedule and that it was completed on time.

Over the entire installation phase, Goltens Singapore guided the shipyard contractors meticulously to ensure there were no delays to the project schedule and that it was completed on time.

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/techcross-bwts-retrofit-for-lng-carrier
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=techcross-bwts-retrofit-for-lng-carrier&page=
Loaded Template: single-resources.php
Search Goltens ×