be_ixf;ym_202411 d_22; ct_100

Time Wasted - Should Have Waited For Goltens

GOLTENS RECTIFIES DAMAGED INTERMEDIATE PROPELLER SHAFT AFTER COMPETITOR FAILS

A recently built general cargo vessel experienced a bearing failure on its intermediate propeller shaft bearing. Goltens was contacted to perform an inspection on the bearing shell and pedestal and to propose a solution. Upon inspection it was determined that the entire housing would require repair, due to extensive damage on the bearings, sealing areas, and housing mating surfaces. Further, an inspection of the shaft showed areas of high hardness but no signs of cracks. Goltens proposed that the bearing housings be sent to its workshop for repair and that the intermediate shaft be machined 1.00 to 1.5mm to remove the hardness and clean the running surface. Goltens was awarded the repair of the bearing housing, but the owner awarded the shaft repair to Goltens’ competitor as Goltens’ specialists would not be available for a few days due to other ongoing jobs.

  • Damaged intermediate shaft journal prior to repair by Goltens

    Condition of journal after competitor failed

  • Goltens in-place machining tooling mounted on intermediate shaft journal

    Journal machining in process with custom tooling

  • Goltens In-place machinists repair damaged intermediate shaft journal

    Journal machining in process with custom tooling

  • Goltens repairing damaged bearing housing

    Machining out the damaged labyrinth seals

  • Goltens checking journal bearing roughness after machining

    Checking surface roughness after journal polishing

  • Repaired propeller shaft journal after in-place machining by Goltens

    Propeller shaft journal repaired

  • Repaired bearing housing for intermediate shaft by Goltens

    Bearing and Labyrinth seals installed

  • Bearing housing ready for installation by Goltens

    Bearing housing repair complete

  • Goltens Chockfasting and jack testing of intermediate shaft

    Lower Bearing Chocked undergoing jack test

  • Repairs completed by Goltens on intermediate propeller shaft journal and bearing housing.

    Upper housing installed – repairs complete

HOUSING AND BEARING DAMAGE

Goltens received the bearing housing in the workshop and set to work repairing it. The heat from the failure had caused the lower housing to collapse 0.8 to 1.0mm and the labyrinth seal cast into the housing was badly damaged. Goltens set to work machining the mating surfaces to restore flatness, along with machining out the forward and aft labyrinth seals. Final machining would be delayed until the finish diameter of the shaft and custom bearing shells was known.

SHAFT MACHINING

Goltens had proposed to complete the machining in 5-7 days on-site. After multiple weeks and failed attendances, the company initially selected to do the repair gave up on machining the shaft. Ship owner contacted Goltens, and within the same day, Goltens readied the custom tools and deployed machinists to undo the damage and complete the needed machining repairs.

Upon inspection, Goltens found multiple scoring marks from the failed machining, as well as taper that ran 350mm along the shaft length with high ovality. Radius grooves were machined at the edge of the shaft for alignment of the in-situ machines and Goltens proceeded to remove 0.30mm from the shaft to correct ovality and taper. Once ovality was removed, a deep radial groove caused by the other company, remained on the shaft surface. This required Goltens to machine an additional 0.30mm prior to final honing and polishing the shaft surface.

FINAL STEPS – INSTALLATION AND TESTING

Goltens finished the machining in seven days with a final diameter of 367.30mm. A custom bearing was machined to a +.55mm inside diameter, with cast iron labyrinth seal inserts fabricated and locked into the housing set to an inside diameter of 370.00mm.

Goltens then transferred the repaired pedestal bearing to the vessel and rigged it into place and aligned the bearing. A successful jack up test was then performed on the shaft with 6.3 tons before reaming the fitting bolt holes and installing the fitting bolts in place. Goltens then poured the Chockfast foundation and waited for the compound to cure before tightening the foundation bolts. Final scraping adjustments were made to the ensure the right clearance before a final jack up test was completed. The bearing was then reassembled and tested at low RPM with satisfactory oil flow.

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/time-wasted-should-have-called-goltens-first
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=time-wasted-should-have-called-goltens-first&page=
Loaded Template: single-resources.php
Search Goltens ×