be_ixf;ym_202412 d_21; ct_50

Goltens Green completes second Hyde Guardian BWT retrofit for Seaboard Marine

Goltens Miami and Goltens Netherlands team up for transatlantic BWTS retrofit

Having completed a similar retrofit for the Seaboard Atlantic in 2014, Seaboard Marine , a major container operator in Miami, again contacted Goltens Green Technologies’ specialists in Miami to undertake and manage the end-to-end retrofit of a Hyde Guardian HG250GC ballast water treatment system onboard the Seaboard Patriot.

Goltens’ team in Miami met with Seaboard to discuss the timing and scope of this second ballast water treatment retrofit project. This one was different as it included completing the installation of the system during dry- docking in Rotterdam in October of 2015.

To drive project efficiencies, Goltens Green Technologies in Miami logically proposed that Goltens Green Technologies in The Netherlands manage this project. The project was started in June of 2015 with 3D scanning of the vessel while in port in Rotterdam.

  • Goltens Hyde Guardian BWT retrofit

    Seaboard Patriot

  • 3D Scan of Hyde Guardian BWT retrofit

    3D Scan of Ballast Pump Area

  • 3D Model of Hyde Guardian Ballast water system overlaid on scan

    3D Model of Ballast water system overlaid on scan

  • Hyde Guardian BWT system installed by Goltens

    Ballast water system installed per design

  • Hyde Guardian BWT retrofit by Goltens

    3D scan

  • Hyde Guardian BWT retrofit by Goltens

    model and installation of filter and piping

  • 3D scan modeling for Hyde Guardian BWT retrofit by Goltens

    3D scan premodeling

  • Hyde Guardian BWT retrofit by Goltens

    3D model overlaid on scan

  • Hyde Guardian BWT retrofit by Goltens

    Filter and piping installation in progress

PROJECT FACTS

SEABOARD PATRIOT BWT RETROFIT
Ballast Water System: Hyde Guardian HG250GC
System Capacity: 255 m3/h
Customer: Seaboard Marine
Vessel Type: Container Vessel

HYDE GUARDIAN BWT SYSTEM RETROFIT SCOPE

  • 3D Scanning, Survey and Modeling
  • Detailed engineering including pipe isometrics, foundation drawings and an installation manual
  • Pre-fabrication of all required piping and materials
  • Delivery of complete, prefabricated installation kit to shipyard in Rotterdam
  • Electrical installation
  • Project management and oversight of the installation in the shipyard
  • Commissioning of the system with Hyde technical representative

BWT RETROFIT RESULTS

As planned, all piping and installation materials were delivered to the shipyard in September of 2015. Installation by the shipyard went smoothly and was completed and commissioned on time in October 2015. The installation was fully reviewed and approved by vessel’s class, Bureau Veritas.

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/transatlantic-bwts-retrofit-for-seaboard-marine
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=transatlantic-bwts-retrofit-for-seaboard-marine&page=
Loaded Template: single-resources.php
Search Goltens ×